Building Statistics

 

 

 

Part 1

 

General Building Data:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Photo Courtesy of Noritake Associates)

 

 

Project Team:

Owner │Hoffman Company │www.hoffmantowncenter.com
Construction Manager │Balfour Beatty Construction │www.balfourbeattyus.com Architect │Noritake Associates │www.noritakeassociates.com
Mechanical & Electrical Engineer │Allen & Shariff │www.allenshariff.com
Civil Engineer │Christopher Consultants │www.christopherconsultants.com Landscape Architect │Studio 39 Landscape Architecture, PC │www.studio39.com Structural Engineer │Fernandez & Associates Structural Engineers, P.C. │ www.fernandez-assoc.com

 

Architecture:

 

The Hoffman One Building is a 4 Phased Renovation project based on a tenant fit out. Currently the project has only been awarded Phase 1. The existing scope of work for Phase 1 includes the construction of a new façade, roof, main lobby and the renovation of elevators, core interior spaces and new penthouse equipment. Phase 2 will consist of completion of the 2nd floor restrooms. Phase 3 and 4 will be contingent on securing a tenant, and will be performed under a separate contract. The building is encased with precast architectural concrete panels, window glazing, and decorative CMU block walls at the buildings entrance and second floor.

The location of the Hoffman One Building is a unique area due to its close proximity to Old Town Alexandria in Virginia. Old Town Alexandria has a historical value and authenticity within its municipality, allowing the Architectural integrity to be mandated within this region. Having said that, due to the location of the building the renovation was not affected by the historical requirement. The Hoffman One Building was carefully designed in regards to the surrounding town and areas existing conditions. Moreover, although Old Town Alexandria contains historical value, the Hoffman One was not directly dependent on the same principles.

 

Code:

The proposed type of construction for this governmental office building is classified as Type 1B with Non-Separated Mixed Uses, Fully Sprinklered. Type 1 B refers to the fire resistive, non-combustible ratings for exterior walls, structural frame, ceiling/floor separation, and ceiling/roof assembly. This classification is based on mid-rise office and group R buildings similar to the Hoffman One Renovation Project. There is no change in occupancy due to the renovation of the Hoffman One Building being a tenant fit out renovation. Maximum number of occupants per floor from levels 3-14 is equivalent to 246 occupants or less per floor. Minimum requirement for stair towers is 2 with 123 occupants per stair. The building height is 14 stories at 149’-6”, including roof level parapet. Main roof high point from average grade is set at 146’-0”.

 

The following national code models were utilized to inform the Hoffman One Building design:

 

2009 Virginia Uniform Statewide Building Code

2009 Virginia Rehabilitation Code
2009 Virginia Statewide Fire Prevention Code
2009 International Building Code (with ANSI A117.1-2003 for accessibility) 2009 International Energy Conservation Code (with ASHRAE 90.1-2007) 2009 International Mechanical Code
2009 International Plumbing Code
2008 National Electric Code
2009 International Fire Code
2003 ICC/ ANSI A 117.1

 

Zoning:

The zoning code in affect for this project is in regards to the City of Alexandria zoning ordinance, which is CDD-2. Coordinated Development District designed a common vision for the future of the community based on planning process. The City Council policy initiatives and actions affecting land use, zoning, capital improvements and programs in the Potomac Yard / Potomac Greens area. The zoning ordinance contains the minimum lot size, frontage, setbacks, open space, and various other qualities. The CDD is a zone established for large areas that will have significant development related impacts on the city and to promote development consistent with the master plan. Properties that develop using the CDD zoning must apply for a Development Special Use Permit (DSUP) [alexandriava.gov].

 

Historical Requirements:

There are no historical requirements for this building.

 

Building Enclosure:

The project is located adjacent to a retail building, and shares a loading dock area with Hoffman 2 office building. The connection of these buildings is through an area, called the Annex, which is used for material storage during construction and renovation. Both of these existing buildings will be in operation during construction. With the surrounding buildings, the Hoffman One Building has a variety of façade features and conditions that encompass the perimeter of the building.

 

 

North Elevation:
The North façade of the building includes precast
architectural concrete panels in 25-foot lengths
with exterior wall
performances required for the
building envelope. These were
assembled by hoisting the panels
into place using a crane, then
anchored and set with the
assistance of the connecting
crew.

 

 

 

East Elevation:

On the East façade of the
building, which differs from the
remaining elevations, is captivated with metal spandrel panels. These panels are a unique feature and were designed because of the surrounding retail stores within the Hoffman Town center. The reason for this was because of crane coordination and construction sequencing. To perform any picks or lifts over an existing, occupied structure, the entire area must be cleared. This was not an ideal process for scheduling; therefore it was in the owner and the architect’s best interest to design a light gauge metal spandrel system to be installed from inside the building structure.


South Elevation:
As for the South elevation, which will serve as the main entrance to the building, displays a glass curtain wall system designed with extruded aluminum member frames. Additionally there is vestibule that is encased in glass, which rests on a slight 25-degree angle to the accompanying occupants and visitors as they approach the building from the south elevation. The reason for this design was to act as if the

building was drawing the visitors in, creating an inviting sensation from the main entrance of the building.

 

Roofing/Penthouse Level:
One of the most unique features when visually analyzing the facade of the building is the mechanical risers that scale the exterior of the structure. These are the “V” shaped objects, that appear to be structural bracing for wind loads, but in fact are not. Surprisingly, these are the mechanical risers that complement the building and are an architecturally pleasing ascetic. Each mechanical riser contains a chilled water supply and split tee system encased in the chases. Designing these mechanical risers was a crucial feature to the project, due to the request for 9-foot ceilings. When designing a system for an existing structure, the renovation process can be quite straining. However, the result to ensure the availability and space from within the core, a portion of the mechanical system was required to reside on the building envelope, thus resulting in the mechanical risers. There will be a new roofing system over the existing concrete deck, along with concrete surface leveling at the penthouse roof level.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sustainability Features:

The project will be constructed to achieve a US Green Building Council (USGBC) LEED SILVER rating in the CS (Core & Shell) category under the requirements of Version 2009; which is contingent upon the owner securing a tenant. With that said, there is still LEED tracking and documentation to ensure that all necessary details are recorded. This will warrant the Owner to receive high efficiency gains in return once a tenant is secured. Throughout the tracking and documentation process there are a variety of LEED categories. These classifications include public transportation, recycled materials, site location, and energy consumption. One of the most popular LEED categories utilized on this project is the transportation of construction materials. Based on the location of the product and the construction site, LEED points can be attained by ensuring that distance is less than 500 miles. Another example is the location in respect to the metro station. When projects seeking LEED accreditation utilize and record the public transportation aspect additional points can be earned. Categories are based on the building’s performance in regards to the sustainable system upgrades and construction process within the renovation sequence. 

Part II 

 

 

Construction:

 

The Hoffman One Building is currently under construction and in Phase 1 of the renovation project.  Similar to any building in the early stages of construction, there are always a variety of opportunities and threats that will arise as usual. The unique factor in regards to the Hoffman One is that there has been a great deal of focus to avoid any delays or potential threats.

 

 

With that focus, there have been multiple constructability concerns or challenges on the project. The most crucial constructability concern in terms of scheduling and coordination was the defective glass that was delivered and installed. Progressing through the schedule was a great success with crews working effectively and performing quality work on a daily basis. It wasn’t until after installing level 2 through 10 when a variety of window glass panels were noticed to have pink streaks appearing through the glazing fill.

After evaluating the situation, the number of glass panels began to increase throughout the building. With the building only about 4 floors away from being enclosed, there was an unforeseen error in the glass.

Coordination was key at this point, which is why the Owner, General Contractor, Subcontractor, and Manufacturer held a project solution meeting. The idea of developing a recovery plan was immediate; the project manager took the lead with the help of the subcontractors’ commitments and flowed a 4-week recovery plan.

As mentioned the building was now in the stages of being enclosed, which meant that the floors were no longer open for crane access and pick deliveries per floor. This created a minor issue, which threatened a delay on the project.

In order for the installation of the glass to occur the glass panels were delivered to each floor by the elevator. This was a major time delay for production; accessing the elevator with a 6’ x 3.5’ window panel was not very effective. The glass was removed from each floor due to the fabrication error on the glass. To ensure that the glass could be uninstalled at a reasonable pace, the Northwest corner on the 1st floor storefront was left open to increase production and removal. Unfortunately, the glass was not qualified for recycling.

One concern is in regards to the recent MEP coordination for the installation of the men and women’s bathroom located on the second floor level. The issue is that the existing structure specifically in the women’s bathroom is affecting the current design for the project. The owner desires 9-foot ceilings within the building, which is an issue when the existing beam is currently penetrating through the women’s handicap stall at precisely 7’-10” to the bottom of the beam. Through multiple efforts to ensure a timely delivery and the quality of the project, the MEP coordination pursued the resolution of constructing a bulkhead in that specific stall area. The reason this is not a significant issue is because the stall is a handicap accessible stall, therefore there are not height requirements or contingences.

 

In addition to the MEP coordination issue, there was a day where activity production was lost due to a permit misunderstanding. The problem was in regards to the design in the asphalt roofing system, which required a specific permit for installation. The permit pertains to the use of a kettle, which is a high risk and safety issue. The general contractor Balfour Beatty, did indeed acquire a kettle permit for this activity, but was shut down by the Fire Company instead. Originally, only a permit was required, but newly developed township codes demand the inspection of a fire company representative for approval. Moreover the activity was in fact delayed for approximately 2 weeks.

 

Although there have been a few issues in terms of construction sequencing and phasing, the opportunities for the schedule acceleration and improvement will be executed. 

 

 

Electrical:

 

 

The main building switchboard is rated for 4000A, 480/277V at 3 phases. The ground floor electrical system will be limited to the parameters with the design and installation of phase 1. The entrance vestibule heater will be wired to temporary service for future use and rough in details. Main lobby lighting will be installed to panel R-1A, which is through the distribution of transformer #2 rated at 2500kVA. There are four main transformers being installed in Phase 1, which are the known as transformer #1A, transformer #2A, utility transformer, and the penthouse transformer. Lastly, the building contains an emergency power system, which is supplied by one generator at 230kW.

 

Mechanical:

 

The Hoffman One Building renovation project’s mechanical system contains one 1000-ton rooftop-cooling tower, which will have an equalizer connection, as well as vibration isolation rail and vibration switch. Additionally, two 5 ton split system heat pump that will serve the main lobby on a temporary basis. Condensing units will sit in the unoccupied second floor tenant spaces, until a tenant is secured. Exterior vertical perimeter chilled water and outside air will be installed with capped connections at the mechanical exterior risers. The system consists of four 5kW unit heaters at the 14th floor level.

 

The penthouse/roof level will contain exterior vertical perimeter of outside air duct and distribution ductwork on the roof. These will be installed with the capped connections as mentioned previously, in the penthouse, which will be for future extension in later phases of the project.

 

For Phase 1 there will be (5) total Air Handling Units which will serve the lobby-east and west zones, the 2nd floor-east and west zones, and two our interior areas for the east and west zones for a typical floor. The air handling units for the interior and lobby area will range from 1200CFM-1700CFM, as for the 2nd floor AHU, it will total approximately 8100CFM. For future tenant equipment, there will be a chilled beam system, equating to four beams that will be passive at a nominal capacity of 200BTUH/LF. Lastly there will be (7) 2-pipe fan coil units installed for future tenant use, (2) of which will be utilized in Phase 1, whereas the remaining (5) will be for later Phases.

 

Structural:

 

The Hoffman One Building is a concrete structure supported by foundation walls (12”-24” in thickness) and spread footings on resourceful existing soil. In regards to the actual renovation project, the Hoffman One Building is not acquiring additional structural systems or supports to a great extend. With that being said, the renovation project will include an additional grade beam at the south elevation of the building below grade, as well as structural steel framing at the penthouse/roof level, and at the front entrance of the building. The grade beam within the soil is a A-36 at approximately 35’.

 

The structural steel framing at the penthouse can be seen in the figure 1 below, which was taken shortly after the erection of the system. There will be a new wind post column pier 20”x20” w/ 4-#7 vertical and 4-#3 at 4” o.c ties at the penthouse roof level. The structural system will be supported by (16) base plates with the majority of them being 16”x16”x1/2” base plates. The vertical and horizontal steel supports will consist of newly added HSS 8”8”x5/16” at differing lengths and heights. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Figure 1: Courtesy of John McCoach)

 

As for the structural steel located at the front entrance, it consists of a curtain wall system; a diagram displaying the structural steel for the building’s vestibule can be viewed in the figure 2.  The system consists of (2) base plates at the front entrance, which contain a 10”x10”x3/8” w/ (4)-1/2” o.c, for a 2” recessed finish below new grade. Additionally the structure will contain (2) base plates at 20”x20”x3/4” w/ (4)-3/4” o.c at level grade slab. The (2) main supports consist of HSS 2”x12”x3/8” columns that extend to the underside of the third floor, since the lobby area will be exposed. The vestibule framing mostly consists of HSS 3”x8”x3/8” structural steel. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Figure 1: Courtesy of Superior Steel)

 

 

Fire Protection:

 

The Hoffman One Building will contain a sprinkler system throughout the entire building, which will allow for one hundred percent coverage to provide adequate fire protection. The existing structure contains a fully automatic standpipe system, class 1, which will aid in the overall fire protection system. Elevator shafts will encase sprinklers within the shafts to ensure safety. The current fire company in jurisdiction of The Hoffman One Building is the Alexandria Fire Department Station/Engine #204.  Lastly, pertaining to the elevator shafts and lobby location there is an authorized Knox box rapid entry system for life safety-fire & rescue operations.  

 

 